Mid Term Quiz

MTH601 – Operation Research | Mid Term Quiz

Welcome to your MTH601 - Operations Research

1. 
Which of the following correspond to the practical limitation of available resource while modeling a real life situation into a linear program

2. 
Which of the following method follows iterative procedure to solve a linear programming problem?

3. 
Solution region of the constraints :2x+3y>12 and 2x+3y

4. 
In the graph of the purchasing model with shortages the area under the horizontal axis represents________.

5. 
The straight line associated with the constraints 2x+3y

6. 
Which of the following value is correct for the expected time of an activity having optimistic, pessimistic and most likely times as 4,8 and 6 days.

7. 
In a network flow a diagram for an activity(I,j) of duration of three days if its earliest start time is of two days then which of the following will be its early finish time?

8. 
In a development project. If an activity (m,n) of seven days duration starts late on 5rd day then which of the following will be its latest finish time?

9. 
Which of the following is an intermediate step to model a linear programming problem?

10. 
A/An ________ is the collection of inter related activities to be performed in a particular sequence to completion.

11. 
Which of the following times are directly to the activity cost that is by reducing the activity duration the direct cost of the corresponding activity is increased?

12. 
Which of the following is an operation research (OR) process?

13. 
In the purchasing Model with shortages the cost function C(S,Q) can also be expressed as function of_______.

14. 
Which of the following would be the objective of the yield per minute in a chemical process which depends upon the temperature ‘x’ and pressure ‘y’?

15. 
Which one of the following is not an operations research problem solving steps?

16. 
In the Dynamic order Quantity if the ratio of setup and carrying costs is 500 and the demands of 2nd and 3rd months are 50 and 130 respectively then which of the following is true about the 2nd months requirement?

17. 
The mathematical technique which is used to solve a wide class of problems such as allocating scarce resource among competitive activities is known as_____.

18. 
Which of the following would be the objective of the cast per unit of producing certain cameras?

19. 
In CPM each activity has one deterministic time while in PERT each activity has_____ probabilistic time/times

20. 
In the phase of early start and early finish to find the critical path in a network flow diagram the computation are proceeded from_____ to the final event.

21. 
In a development project, if an activity(I,j) of six days duration starts late on 3rd day then which of the following will be its latest finish time?

22. 
If the annul demand of a product is 10000 items , and its set up and inventory costs are 200 and 100 respectively then its economic order quantity is________ provided that shortage is fulfilled INSTANTANEOUSLY.

23. 
For a LP problem say,Max.z=x+y, under the condtraints xy>=0 the feasible region would be___________.

24. 
By which of the following method any complex linear programming problem can be handled?

25. 
In the phase of Early start and early finish to find the critical path in a network flow diagram flow diagram, for the first node(event) we start will time________.

26. 
Solution region of the constraints 2x+3y>12 or 6x+9y=36 Will be the half plane bisected by 2x+3y=12.

27. 
Which of the following event has no immediate predecessor in any network flow diagram?

28. 
Which one of the following is not an operation research problem solving steps?

29. 
For critical path of a network which of the following is the best suitable answer.

30. 
If the economic order quantity and the annual demand of a product are 2500 and 5000 units respectively then without any shortage the time between the consecutive order is _________ months.

31. 
Which of the following quantity will very in case of Dynamic order quantity model?

32. 
Which of the following will be annual optimum cost of a product if the number of annual orders without any shortage is 25 and the total cpst of one cycle is 10,000?

33. 
Which of the following would be the objective of the daily loss of heat in a heating system?

34. 
While applying Simplex method to a LP of minimization type, we proceed stepwise from one______ solution to another in such away that the objective function always increase its value.

35. 
The amount of the inventory will always taken to be _______.

36. 
Solution of a Linear programming problem is found by______ methods.

37. 
A critical path in a network flow diagram____.

38. 
In the dynamic order quality problem the demands of all succeeding months can be included in the demand of preceding one provide that_______.

39. 
Which of the following property ensures that the decision variables can be divided into any fractional levels so that the rational(fractional) values for the decision variables are permitted?

40. 
In the ABC analysis the items are classified into three categories with respect their______

41. 
If for path 1-3-4 times is 5+3-8 days for path 1-2-3-4 time is 6+7+3-16 days and for path 1-2-4 time is 6+6-12 days then which of the followings id ture

42. 
Under which of the following condition a mathematical program would be non-linear?

43. 
In which of the following model the carrying cost per unit of time is reduced in the ratio (1-D/R):1?

44. 
Which of the following technique to solve the network flow diagrams is activity oriented?

45. 
In resource leveling when two or more jobs complete for some resource first try to allocate on activity which is of_____ duration end next to the activity which having next____duration.

46. 
The objective function and___together from a linear programming problem.

47. 
Which of the following property must be satisfied by a linear programming model?

48. 
In pert the possible variation in activity can be measured from______ of the corresponding beta distribution.

49. 
Which of the following is not a categories of the operation research (OR) techniques.

50. 
In a project management if the critical activities of a network are delayed then_____

51. 
EST and EFT of activities are calculated in

52. 
_________________ may be less than most likely time estimate

53. 
The dummy activities consume

54. 
If an activity consumes no time and no resources then this activity is called __________

55. 
Cost period ------- ( No of ordered items)

56. 
The following network is an example of

57. 
The following network is an example of

58. 
If t0 = 6, tm = 12 and tp = 18, then Vt= _________

59. 
Which one is best describe Micro Economic Planning?

60. 
If t0 = 6, tm = 12 and tp = 18, then Vt= _________

61. 
Which inventory model also known as a saw tooth model?

62. 
For backward pass computations

63. 
For an activity if optimistic time, most likely time estimate and pessimistic time estimate are 3, 6 and 15 respectively then expected time is

64. 
In a quadratic programming problem unlike linear programming problem

65. 
- Solution region of the constraint x≥ 0

66. 
A dummy activity is a simulated activity of sorts, one that is of ________duration and is created for the sole purpose of demonstrating a specific relationship and path of action on the arrow diagramming method.

67. 
Activity definition refers to the process of parsing a project into a number of individual tasks which must be completed ___________ the deliverables can be considered completed. Activity definitions rely on a number of specific input processes.

68. 
A forward pass is used to determine and calculate the ________________ dates, through utilization of a previously specified start date.

69. 
Total cost per period = Item cost + Order cost + Holding cost + _____________.

70. 
K= Z x (_ _ _) Where K is called service factor

71. 
_______________ employs a different modeling and solution logic than linear programming

72. 
To identify and maintain the proper precedence relationship between activities those are not connected by event, we introduce

73. 
EST and EFT of activities are calculated in

74. 
Critical path is obtained by connecting the jobs having

75. 
In LP problems Additively means that

76. 
Two of the first steps of OR process encompass the actual use of OR techniques. These steps are

77. 
Let FS = Free Slack, TS = Total Slack, INDS = Independent Slack, then which relation is true

78. 
Best possible time estimate that a given activity would take under normal conditions which often exist, is called

79. 
Standard Deviation S.D is

80. 
Is this Network legal?

81. 
In the relation of finding the expected time of an activity, most likely time is weighted more than the other optimistic and pessimistic times and these exist in the ratio of -----------.

82. 
In PERT, the possible variation in activity times can be measured from -- --------- of the corresponding Beta Distribution.

83. 
Which of the following Probabilistic time in PERT has the same analogical meaning of Deterministic time (time to complete any activity) in CPM?

84. 
About which of the following it is true that, “they only signify with the passage of time, the beginning and ending of some activities under no consumption of resources” ?

85. 
While solving a network flow problem by PERT, which of the following type of time will be used to measure the length of Critical Path?

86. 
In a project, a network diagram shows the precedence relations of inter related activities along with their corresponding activity ----------.

87. 
The network flow diagrams for PERT and CPM are same except for ------ -----.

88. 
Which of the following relation is true among the probabilistic times in PERT?

89. 
Which of the following relation is correct for the Standard Deviation of an activity times having optimistic, pessimistic and most likely values as 4, 8 and 6 days respectively?

90. 
In a project, a network diagram shows the ------------ relations of the inter related activities along with their corresponding activity times.

91. 
The task which is executed by the usage of resources and time is called -- -----------.

92. 
- If both jobs ‘a(l,n)’ and ‘b(m,n)’ of ‘7’ and ‘8’ days durations respectively, start earlier simultaneously on 4th day, then ‘n’ can start earlier on -----------day.

93. 
In a network flow diagram, if an event is the predecessor of three other events then how many dummies are inevitable to include in the network?

94. 
- In a transportation problem the objective function 'Z’ gives____ .

95. 
In two phase method process, first phase___ the sum of artificial variables.

96. 
Which of the following difficult may found while attempting an LP problem by M-method?

97. 

98. 
For finding the maximum profit in an enterprise of selling two products such that freezing the sale of one product and keep selling the other. This scenario is studied under__________.

99. 
Which of the following will be an example of degenerate basic feasible solution for an LP problem?

100. 
Under which of the following condition to solve an LP by using two phase method we can’t proceed for 2nd phase?

101. 
A balanced transportation model with 5 number of source 7 destinations has ___ number of constraint equations.

102. 
Dual of a Dual is ____________.

103. 
Shortcoming of Big M method is that the value of M could be ______.

104. 
In simple method to solve an LP problem gauss Jordan Elimination method demands that all the key column enters should be zero except ____.

105. 
The cost coefficient of artificial variable in objective function is _____.

Leave a Reply

Your email address will not be published. Required fields are marked *